Timeline

 

 

April 2, 2002
Location Announcement
 
April 16, 2002
Groundbreaking Ceremony
 
November 2002
Start of Construction
 
February 19, 2003
First Steel Beams Erected
 
February 23, 2003
Production and Maintenance Advertisement
 
Fall 2003
First Production and Maintenance Hires
    
January 5, 2004
Production Team Members Start Work
 
 
January 5, 2004
HMMA 2004 Kick-Off Event
 
January 2004
Some Maintenance and Production Team Members Go to Korea for Training
 
February 5, 2004
The first of HMMA's two 5,400 ton stamping presses departs from Tokyo, Japan
 
March 9, 2004
The stamping press arrives at Alabama State Port Authority’s Pier D-2 in Mobile. The 268,520 pound crown and 262,171 stamping bed of the press are transported via barge up the Alabama River. The remaining parts are loaded onto more than 80 trucks for transport to the HMMA Plant Site
 
March 15, 2004
Crown and stamping bed of the press arrive in Burkeville via the Alabama River and are loaded onto dual lane trucks for transport to the HMMA Plant Site
 
June 2004
Completion of Facility, Part-Time Trials Begin
 
July 2004
Trial Production of the Next-Generation Sonata Begins

 

Ribbon Cutting Group

 

May 20, 2005
Grand Opening Ceremony
  
Spring 2005
Job 1 Vehicle Production Begins
 

Santa Fe Rolling Down Red Carpet

April 18, 2006
Production of the Next-Generation Santa Fe Begins

 

2007
Plant approaches full capacity producing approximately 1,200 vehicles per day.

May 2007
Breaks ground on new 4-cylinder Theta engine plant

September 2008 
Theta engine plant begins producing 4-cylinder engines.

November 2009
HMMA produces its 1,000,000th vehicle.
/uploadedImages/Media_Center/News_Releases/2009/_MG_0674.jpg 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 



 